Project Status

From Application to Defense

A diploma project runs for a whole school year. Here you can openly see what is finished, what we are currently working on, and what is still pending (including the things that won't work on the first try).

3 of 20 milestones reached · As of October 2026

September 2026done

Application and Project Start

Definition of goals, object breakdown structure, work breakdown structure, stakeholder and risk analysis, budget of 7,200 to 7,700 euros, and the milestone list. The application was submitted on September 24th, this website was launched on the same day. The base vehicle is already in the workshop.

October 2026up next

Digitization and Design

3D scan of the frame and remodeling in CAD, component design with an initial battery pack mockup, electronics specification, and first laboratory tests.

November 2026open

Construction and Motor Control

Construction of the motor and motor controller mounts, pitch presentation to a professional audience, programming, and commissioning of the motor control.

December 2026open

First Test Drive and Battery Pack

The initial test drive with the prototype, in parallel the CAD design of the battery pack as well as cell connection and spot welding.

January 2027open

Integration and System Test Drive

Completion of the battery pack, integration of the drivetrain and display, and finally the test drive with the complete system. This is where we'll see if the 65 km/h and 45 km hold up.

February to May 2027open

Documentation, Presentation, Defense

First draft of the written thesis, approval, final presentation of the diploma projects, correction copy, and on May 21, 2027, the defense.

Overview

All 20 Milestones

The target dates from the project application, continuously updated.

# Milestone Target Date Status
1Application for admission to diploma project submitted24.09.2026done
2Information website launched24.09.2026done
3Database submitted05.10.2026done
43D Scan and Digitization10.10.2026up next
5Component design and battery pack mockup25.10.2026open
6Electronics specification and lab tests25.10.2026open
7Construction of motor mount05.11.2026open
8Construction of motor controller mount15.11.2026open
9Pitch presentation of diploma projects24.11.2026open
10Motor control and commissioning25.11.2026open
11Initial test drive (Prototype)14.12.2026open
12Battery pack design in CAD14.12.2026open
13Cell connection and spot welding28.12.2026open
14Completion of battery pack06.01.2027open
15Integration of drivetrain and display10.01.2027open
16System test drive (Complete System)15.01.2027open
17First draft of the written thesis08.02.2027open
18Diploma thesis approved05.03.2027open
19Final presentation and correction copy12.03.2027open
20Defense21.05.2027open
@tesmos.htlrennweg Workshop pictures, measurement series and everything that breaks in between. We post at least every three weeks.